Power-Plant

Gas based captive power plant of 62.5 MW capacity outGas based captive power plant of 62.5 MW capacity out of which 2 nos. of steam turbo generator of each19.25 MW and one gas turbo generator of 24 MW capacity. Besides this, power plant has three nos. of gas-fired boilers of each 65 t/hr capacity, one steam turbo blower, one electric turbo blower, and one heat recovery steam generator of capacity 45t/hr for recovery of heat from flue gas of Gas turbo generator.

 



The power plant has been designed on the concept of full utilization of surplus fuel gases such as blast furnace gas, converter gas and coke oven gas .No external fuel is used for steam generation. LDO is used for flame stabilization

 

 

 

NINL is self sufficient in power and is exporting substantial quantity of power.